Construction of Garobadha to Dalu NH-51 in Meghalaya completed more than 50 Pc

New Delhi, April 12: Construction of ten roads and some major bridges of a total length of 433.225 Km under the North Eastern States Roads Investment Programme (NESRIP), an Asian Development Bank (ADB) assisted road project,  is presently under implementation.

The State Public Works Departments in the six states are the implementing agencies.  In Assam, the work has been completed Bilasipara to Fakirgram NH-31 and under the second project Barpeta to Kalitakuchi in Assam and Garobadha to Dalu NH-51 in Meghalaya, more than 50% of the work has been completed. As for the remaining projects, progress is at different stages of construction ranging from 10% to 42%.